Crystal Springs/San Andreas Transmission System Upgrade
OwnerSan Francisco Public Utilities Commission
LocationSan Mateo, CA
Scope of Work45,000 Square Feet
Schedule36 Months
General ContractorKiewit Infrastructure Group
ArchitectSan Francisco Public Utilities Commission
EngineerSan Francisco Public Utilities Commission
Project Summary
New electrical substation, new (4)-pump pump-station and upgrades at reservoir outlet structures; transmission system upgrade, water pumping and new substation.